Daily maintenance of high speed CNC drilling and milling machine
Daily maintenance of high speed CNC drilling and milling machine
In order to give full play to the role of equipment, reduce the occurrence of failures and extend the average time of equipment failure free. Nc drilling machine manufacturer era bystronic customer asked me oh, programming of CNC equipment, operation and maintenance personnel must undergo specialized technical training, have the mechanical processing technology, hydraulic, measurement, automatic control, such as knowledge, so as to fully understand and grasp the numerical control equipment, can increase numerical control equipment maintenance and maintenance work.
The operators of CNC drilling and milling machine should strictly abide by the operation procedures and equipment daily maintenance and maintenance system, and strictly operate the equipment in accordance with the requirements of equipment and system specifications, so as to avoid affecting the use of equipment due to improper operation.
The following are the daily maintenance contents and requirements of the numerical control drilling and milling machine provided by the company:
1. Regularly check the oil content of the lubricating oil tank, add lubricating oil in time, and the lubricating pump can start and stop oil production in time.
2. Remove chips and dirt from X and Z axial guide surface, check whether the lubricating oil is full or not, and check whether the guide surface is damaged by scratches.
3. Check the pressure of the pneumatic control system with the compressed air source within the normal range.
4. Air source automatic water filter; automatic air dryer timely clean the water filtered from the water distributor to ensure the normal operation of automatic air dryer.
5. Check the hydraulic balance system to balance the pressure, and the balance valve works normally when moving quickly.
6. There is no abnormal noise in the oil tank and oil pump of the hydraulic system of the equipment, and the pressure gauge is normal. There is no leakage in the pipeline and all joints, and the working oil and surface are normal.
7. The cooling fans of each cooling and ventilation device of the electric cabinet work normally, and the air conditioning filter screen is not blocked.
8. Check the input/output device of the control system for looseness and firm contact.
9. All kinds of protective equipment, such as guide rail and protective cover, shall be free of loose and water leakage.
10. Check the height of liquid level at any time for cooling oil tank and water tank, and add oil or water in time.
11. Don't pile up too much with the chip cleaner and avoid sticking and damage.
12. Check the spindle driving belt from time to time according to the specification and adjust the belt tightness. If the belt is damaged, replace it in time.
13. Apply new grease to the bearing pedestal every six months.